Obtaining permits from the National Energy Commission (CNE) is one of the fundamental steps for developing projects in Mexico's energy sector.
However, in practice, many administrative procedures face delays that are not necessarily related to the technical complexity of the project or applicable energy regulation. In many cases, obstacles arise from corporate errors or inadequate management of the administrative procedure.
Below we analyze some of the most frequent problems companies face when processing permits before the energy authority.
The symptom: delays and endless requests for information
A few months ago, a company interested in developing a petroleum-products project decided to start the process to obtain the corresponding permit. The project looked solid: it had investors, a well-structured business plan, and preliminary studies showing feasibility.
Nevertheless, the administrative procedure became complicated from the start. Information requests began to pile up and deadlines grew tighter. What initially seemed a relatively straightforward process turned into one full of delays.
The problem was not the energy project or applicable regulation, but something more basic: the legal structure and administrative management of the applying company.
In Mexico's energy sector it is relatively common for companies to focus on the technical or financial side of the project but underestimate the corporate and procedural aspects needed to process regulatory permits.
In this article, we analyze some of the most common mistakes companies make when applying for permits before the CNE.
1. Poorly structured corporate purposes
One of the most frequent errors is that the applying company does not include in its corporate purpose the energy activities it intends to carry out.
This often happens when a company originally incorporated for commercial or industrial activities decides to enter the energy sector without first amending its corporate purpose.
From a legal standpoint, this can raise doubts about the company's legal capacity to carry out the regulated activity, which may lead to additional requests from the authority and even delays in permit processing.
For this reason, it is advisable for a lawyer specialized in energy regulation to participate in drafting the new corporate purpose together with the notary public.
Golden rule:
Do not leave drafting to a generalist lawyer. A poorly drafted corporate purpose can be the first step toward a permit denial.
2. Lack of knowledge of how the CNE Electronic Document Reception Office works
Another recurring problem is lack of knowledge about how the CNE Electronic Document Reception Office (OPE) works.
In recent years, various administrative procedures in the energy sector have moved to digital platforms. However, many companies and even some advisors are not familiar with how filings, attachments, and documentation must be submitted in these systems.
Seemingly minor errors can cause significant delays, for example:
- uploading incomplete documents
- using incorrect formats
- not responding properly to electronic requests
- not following up on the file within the platform
Therefore, it is essential to study carefully the OPE operating rules to understand how it works and avoid unnecessary requests for information.
We share the OPE Operating Rules published on October 9, 2025: DOF - Diario Oficial de la Federación
3. Legal representatives without sufficient powers
Another aspect often overlooked is review of the powers granted to the company's legal representative.
In many administrative procedures, the attorney acting on behalf of the company does not have sufficient authority to represent the company before the energy authority.
In other cases, the powers have problems such as:
- expired powers
- imprecise wording
- insufficient authority for administrative acts
Before starting any regulatory procedure, it is advisable to:
- check that the power is valid;
- verify that its wording is adequate for dealings with administrative authorities;
- confirm that the type of power grants sufficient legitimacy to act on behalf of the company.
Preventive review can avoid unnecessary delays during the administrative procedure.
Bureaucracy is not your worst enemy: complacency is
In the energy sector, a formal error can quickly become a substantive error.
While a company puts off reviewing its corporate purpose or its representative's powers, the authority's deadlines keep moving and project capital keeps being consumed in unnecessary waiting.
Energy projects require not only engineering, financing, and operational planning.
They also require an adequate legal strategy from the start of the regulatory procedure.
In many cases, the difference between a permit that moves forward and one that stalls is not the energy project itself, but how the administrative procedure is legally managed.
Conclusion
CNE permit procedures require not only proper technical preparation of the project, but also adequate legal structure and strategic management of the administrative procedure.
Companies that anticipate these aspects from the outset usually avoid delays, unnecessary requests, and additional costs during permit processing.
Legal advice on energy regulation
If your company is considering starting a permit procedure before the CNE or faces delays in an administrative procedure, EEEsponda Abogados provides specialized regulatory advice for energy sector projects.
If you need more information about the energy sector, we share the following link: New public retail permit | Esponda Betancourt