The new model interconnection and connection agreement to the National Transmission Grid (NTG) and General Distribution Networks (GDN), published March 17, 2026, redefines the rules for companies participating in Mexico’s electric sector.
This instrument, which replaces prior models, establishes not only new technical conditions but a stricter legal, regulatory, and financial framework. For developers, investors, and large energy consumers, reading it correctly can mean the difference between a viable project and an unviable one.
1. What is the new 2026 electric interconnection and connection agreement?
It is the mandatory contract model for any facility seeking connection to the National Electric System, whether to generate, store, or consume electricity.
The Federal Electricity Commission (CFE) acts as transmitter or distributor, while the National Energy Control Center (CENACE) retains operational control. The National Energy Commission (CNE) is the regulator.
This agreement is mandatory for:
- Power plants
- Energy storage systems
- Load centers (including qualified users and loads ≥ 1 MW)
2. Main changes in Mexico’s electric interconnection agreement
Greater state control in the electric sector
The model strengthens the State’s role in system operation. CFE is the central counterparty, while CENACE may direct execution of the agreement and order interconnection.
This significantly reduces private flexibility and increases reliance on regulatory decisions.
Contract rigidity and less room to negotiate
The agreement provides that its structure cannot be freely modified. Material changes often require CNE approval.
That limits tailoring the contract to each project—a major shift from earlier schemes.
Inclusion of energy storage
For the first time, electric energy storage systems are expressly included in this contract model.
However, they are treated similarly to traditional generation, which may create regulatory challenges for operation and monetization.
3. Legal risks of the interconnection agreement for companies
Missing deadlines
The agreement sets strict dates for building infrastructure and starting operations. Delays beyond six months may lead to termination.
That requires much tighter legal and technical planning.
Enforcement of guarantees
CENACE may enforce guarantees if the project does not proceed as planned—direct financial risk for companies.
Infrastructure costs
The applicant must bear:
- Specific interconnection works
- Possible reinforcement works
That directly affects project economics and must be built into financing from the start.
Heavy regulatory dependence
The project depends on:
- CNE permits
- CENACE instructions
That can cause delays and contingencies outside the developer’s control.
Limits when regulations change
Although a "Change in Law" mechanism exists, it is restrictive—aimed at keeping the contract as unchanged as possible, which may limit adaptation to new rules.
4. Opportunities for companies in the new electric environment
Despite higher regulatory load, clear opportunities exist for companies with the right strategy:
- Early legal planning
- Efficient energy project structuring
- Contractual risk prevention
- Optimized regulatory compliance
Companies that involve specialized counsel from the outset gain a significant competitive advantage.
5. What should companies do about the new electric agreement?
To mitigate risk and capture opportunity, we recommend:
- Determine whether the project needs an interconnection or connection agreement
- Conduct legal analysis before signing
- Assess financial risks from guarantees and infrastructure
- Align regulatory strategy with permits and project timelines
Conclusion: a new standard in Mexico’s electric regulation
The 2026 interconnection and connection agreement is a structural change in Mexico’s electric sector. It strengthens state control, increases private obligations, and raises the legal complexity of projects.
For more information see: DOF - Official Gazette of the Federation
For more on the electric industry: Electric industry archives | Esponda Betancourt
In this context, specialized legal advice is not only advisable but essential to ensure any energy project’s viability.