On 19 August 2026, the new ones were published in the Official Journal of the Federation. General provisions on acquisitions, leasing, contracting of services and enforcement of works of the Federal Electricity Commission, which established a new framework for CFE 2026 contracts.
Its publication is particularly relevant for companies that participate or intend to participate as CFE suppliers and contractorsas the new rules range from the procedures for obtaining a contract to its execution, modification, termination and mechanisms for containing certain acts.
The new rules of CFE 2026 contracts arising from the special arrangements provided for in the Articles of 80 and 81 of the State Public Enterprise Act, Federal Electricity Commission.
In particular, Article 81 empowers the Management Board to issue the general provisions applicable to CFE acquisitions, leasings, services and works.
On the basis of that article, the Management Board endorsed the new provisions by agreement CA-CFE-058/2026adopted at its ordinary session on 13 July 2026.
In agreement with its Article 1 Transitionalthe new supplies found into force on 20 August 2026, i.e. the day following its publication in the Official Journal of the Federation.
In addition, agreeing to the Article 2 Transitionalthe previous General Provisions originally published on 23 June 2015 were reviewed.
However, there is a particularly important rule for contracts currently in operation. Article 3 Transitional provide that the processes initiated and contracts concluded before the entry into force of the new Provisions will continue to be governed by the rules in force at the time of their initiation or conclusion.
Therefore, in the event of any contractual dispute, it will be necessary first to determine which regime CFE contracts is applicable.
Which operations are subject to the new CFE 2026 procurement rules?
Based on the Provision 1the new system regulations the processes and acts related to the acquisition and lesson of goods, contracting of services, execution of works and contracting of related services carried out by CFE in national territory.
This classification is important school the new Procurement provisions for CFE established differentiated rules depending on the contractual object.
For example, when a procurement involves good and services simultaneously, it will be necessary to analyse which of these components represents the high economic percentage of the transaction in order to determine its nature.
This situation can often arise in projects in the electricity sector that combines equipment supply, installation, maintenance, engineering and specialized services.
This is why, before participating in the CFE 2026 contracts it is advisable to correctly identify the legal and technical nature of the object intended to be contracted.
CFE 2026 procurement proceedings: competition, invitation and direct award
The new Provisions provides for different mechanisms through which CFE can contract related goods, services, works and services.
In the field of acquisitions, leases and services, these processes are developed mainly in the Provisions 30-46, while it stops related works and services are regulated mainly in the Provisions 72-86.
Among the processes and mechanisms of CFE recommendation are found:
- Open competition;
- Simplified open competition;
- Restricted invitation;
- Direct award; and
- Minor contracts.
The new Provisions also includes figures such as joint bid, auctions, simultaneous supply and negotiation, depending on the characteristics of the proceeding.
Within the CFE 2026 contracts the importance of the Requirements lien, defined in the Provision 4, part XLVas it constitutions the document in which CFE established the specific bases, conditions, characteristics and requirements of a procurement.
Therefore, it is not sufficient for a supplier or contractor to know the General Provisions. Each proceeding should be analyzed in connection with its corresponding Requirements Package.
How will CFE evaluate offers from suppliers and contractors in 2026?
One of the most important aspects of the new CFE 2026 contracts is that presenting the lower price doesn't need to guarantee to obtain a contract.
In the case of acquisitions, leases and services, the Regulation 44 states that CFE may use the criteria of Cost-Beneficiary Evaluation, Price Evaluation or Point Evaluation.
Stop related works and services, the Regulation 84 Consider the Cost Assessment of the Life Cycle, Price Evaluation and Point Evaluation.
The Point Evaluation allows to improve elements related to quality, experience, specificity and price. For its part, in the case of certain works, the Cost Assessment of the Life Cycle permits to consider aspects related to construction, design, maintenance, maintenance, operation, reinventments, service life and residual value.
For this reason, the companies interested in CFE contracts they must identify from the Requirements Pliego which criterion will be used to evaluate their proposal.
Abnormally low price in CFE contracts 2026
One of the relevant figures of the new regime is the Abnormally low price.
Based on the Provision 4, part XLVI, is considered abnormally low price that mount that is not electable for award by CFE and that results from subtracting a percentage of up to 40% to the average of the preponant prices of offers that have been technically and economically solvent.
The consequence for suppliers is important: offering the lower price does not needarily represent an advantage within the CFE 2026 contracts.
A company that exceededly reduced its economic proposal could be placed under the assumption of abnormally low price and therefore be faced with an offer that is not eligible for award.
Consequently, the economic proposed should be structured taking into account both the costs of the supplier and the evaluation rules established by CFE.
Unrequested CFE proposals: an alternative for innovative projects
Another of the figures that stands out within the new Procurement provisions CFE 2026 is the Unrequested proposal.
In agreement with the Provision 4, part Lis a proposed submitted by a natural or legal entity, outside a procurement proceeding, to provide by contract any property, service, work or service related to CFE.
In the area of acquisitions, lessons and services, this figure is developed in the Provision 46, while for related works and services it is regulated in the Provision 86.
On the basis of both provisions, these proposals will only be analyzed when they represent a innovation or when the present person has exclusionity rights Even in such cases, their recipe does not oblige CFE to analyze them.
If, after the CFE analysis, the proposal is considered to be favourable and the case of exclusive rights provided for in article 83, section I, of the Law on the State Public Enterprise, Federal Electricity Commission, is updated, a direct award may be made, fulfilling the corresponding requirements.
This figure may be particularly relevant for energy, infrastructure, engineering and technology companies interested in developing projects with CFE.
Negotiation within CFE procurement proceedings
The new rules of CFE 2026 contracts they also expressly provide for a stage of negotiation.
Based on the Provisions 43 and 83, CFE may establish this stage when, derived from the Market Conditions Research, it determines that better procurement conditions can be obtained through negotiation.
The negotiating aspects must be identified in the Requirements Annex and only those who have submitted technically and economically sound offers may participate.
The agreements reached must also be incorporated into the relevant minutes and will form part of the offer.
For this reason, the CFE suppliers and contractors they will review from the beginning of the process which elements may be subject to negotiation.
Subcontracting in contracts CFE 2026: limit of 49%
Another change to be considered by the CFE contractors and suppliers are the rules applicable to subcontracting.
In the case of procurement and services, the Regulation 51 provide that, where this is allowed by the Pliego de Requisitos, the Provider may subcontract certain obligations.
However, the cumulative amount of contracts concluded with subcontractors may not exceed 49% of the total contract amount.
In addition, prior to the formation of subcontracting, the consent of CFE must be obtained that the third party has technical and financial capacity.
For related works and services, the Regulation 91 also lays down the limit of 49%in addition to requiring the express consent of CFE.
Subcontracting also does not highlight the supplier or contractor of its obligations vis-à-vis the Commission.
These rules are particularly relevant in the CFE 2026 contracts related to EPC projects, construction, infrastructure, maintenance and engineering.
Guarantees for CFE suppliers and contractors
Guarantees are another element that companies must analyse before submitting to tend in the procurement proceedings. recruitment of CFE.
Based on the Regulation 56in the case of acquisitions, lessons and services, guarantors may be established related to the maintenance of the offer, advances, contractual performance, quality, hidden defects and other liabilities.
For related works and services, the corresponding rules are provided for in the Regulation 95.
The type, amount, validity and conditions will depend on the characteristics of each contract and the corresponding Requirements Package.
For this reason, suppliers interested in CFE 2026 contracts they must consider the financial cost of these guarantees from the structuring of their economic proposal.
Amendments to CFE 2026 contracts: can the mount be created?
The new provisions also regulate amendments to the CFE contracts during their execution.
In the case of acquisitions, leases and services, Provisions 58-63 regulatory aspects related to changes, beliefs or beliefs in the mount, time or duration, delays, extensions and suspension of obligations.
In particular, on the basis of Regulation 59certain contracts for the acquisition, read of goods and provision of services may be created up to 50% of its total amountprovided that the concepts, prices and conditions originally agreed upon are reviewed and the requirements laid down in that provision are met.
For related works and services, contractual changes are regulated mainly in the Provisions 99-103including rules on modifications, delays, extensions, suspension and extraordinary work.
For companies participating in CFE 2026 contracts, properly documenting any change is essential.
The execution of additional works or informal modifications without the corresponding contractual support may subsequently generate gaps controlling their recognition and payment.
Conventional penalties in CFE contracts 2026
Failure to compete with a contract concluded with CFE may have significant economic consequences.
In the area of acquisitions, lessons and services, the Provision 64 allow the establishment of conventional penalties, deductions or, depending on the circumstances, the obligation to compensate damages.
Conventional penalties may be linked to delays in the delivery of good or services, while deductions may be applicable when good have characteristics different from those agreed upon or services are poor provided.
Based on one's own Provision 64conventional penalties and deductions, take together, may not exceeded 30% of total contract amountexcept for the exceptional case laid down in the rule itself.
For related works and services, the Provision 104 allow the establishment of conventional penalties, together other cases, for late execution, non-compliance with critical events, non-compliance with the date of termination or deficiencies related to equipment, materials or services.
In addition, the Regulation 105 allows economic subsections to be applied in certain cases related to delays in the implementation programme.
That is why, before we hold a CFE contract, it is appropriate to identify obligations that non-compliance may result in penalties and to determine their possible economic impact.
Early termination and termination of CFE contracts
The new rules of CFE 2026 contracts distinguish between early termination and termination.
Based on the Provisions 66 and 106, depending on the nature of the procurement, CFE may terminate a contract in advance in certain cases, including fortuitous or force majesty, reasons of general interest, agreement between the parties or as a result of a decision issue within the review appeal.
The termination, for its part, is mainly linked to the break of contract.
For acquisitions, leases and services, the process is regulated in the Provision 67, while for related works and services it is established in the Provision 107.
In both cases, CFE may terminate the contract without first obtaining a judicial or arbitral decision, but must observe the proceeding provided for in the Provisions.
Among other things, the Provider or Contractor will have 15 working days after the relevant notification in order to state what is in their right.
The distinction is particularly relevant for companies with CFE contractsschoolship the economic causes and consequences of both figures may be different.
Review appeal: how to challenge a CFE running?
The new ones Procurement provisions CFE 2026 expressly provide for review.
Based on the Provision 23the appeal is against the decision or against the determination by which a contest or a restricted invitation is declared to be deserted, in whole or in part.
Regulation 23 itself provides that an appeal must be lodged within the following five working days the holding of the public meeting at which the judgment is made known or, where there is no public meeting, on the basis of the relevant notification.
This deadline is particularly relevant for any supplier who disagrees with the outcome of a invitation to tender or CFE procurement procedureas it requires that the legal analysis of the judiciary be transported out practically immediately.
Waiting for serious weeks to review the provenance of a means of defence could cause the deadline to promote it to be over.
Settlement of disputes in CFE contracts
The new rules also provide for mechanisms for the settlement of disputes risking from the CFE contracts.
Based on the Provision 22disputes relating to the interpretation, execution and performance of contracts may be subject to alternative means of dispute resolution in accordance with the rules adopted by the Governing Council.
This possibility may be particularly relevant in CFE 2026 contracts related to infrastructure, construction, engineering and energy projects, where gaps can involve economic and technical aspects of considerable complexity.
What should supplies do in the face of new CFE 2026 contracts?
Companies that currently contract with CFE or intent to participate in future proceedings should review their internal processes under the new regime.
In particular, it is advisable to:
- To determine what the new provisions or the previous regime applications to the processor contract;
- Completely review the Requirements Package;
- Verify corporate, legal, technical and financial documentation;
- Identity the criterion by which the offer will be evaluated;
- Review the economic structure of the proposal;
- Analyse the required guarantees;
- Identity activities intended to be subcontracted;
- Appropriately document modifications, extensions, suspensions and additional work; and
- To react in a timely manner to judgments, penalties, termination or any possible contractual dispute.
Conclusions on new CFE contracts 2026
The new ones CFE 2026 contracts will be developed under a regulatory framework that regulates virtually the entire contractual cycle: from the selection of suppliers and contractors to the execution, modification, termination and eventual dispute related to a contract.
Aspects such as Abnormally low price, the Unrequested proposals, negotiation, the limit of 49% for subcontractingthe different evaluation criteria, contractual amendments and the review appeal oblige suppliers and contractors to carefully review the new rules.
For companies in the sectors energy, electricity, infrastructure, engineering and construction, know the new ones CFE procurement provisions before submitting a proposal can be decisive in reducing risks and protecting the profitability of the project.
Legal advice on contracts CFE 2026
In EEEsponda Abogados We advise suppliers, contractors and companies in the energy and infrastructure sectors that participate or seek to participate in CFE 2026 contracts.
Our agreement includes the Review of Requirements Plies, legal analysis of CFE procurement proceedings, identification of contractual risks, legal review of proposals, negotiation and modification of contracts, review and prevention remedies and resolution of CFE-related disputes.
To read the original text, we share the following link: DOF - Official Journal of the Federation